How Do I Edit The Schedule?

Editing a schedule is very similar to what is done when creating a schedule.

To manually link tasks, click the finish bubble and drag it to the start bubble of the preceding activity.

Drag the Gantt bar to the right to establish the task duration.

Double click on the Gantt bar to open the task details screen, or click the task item on the left column to open the task details screen.

From the task details enter the task start/end date as well as duration, resource, and status.

Add Links to dependent and preceding activities, select the relationship, and add lag time (positive or negative).

Once a relationship is established and needs to be edited or deleted, double click the taskbar to open the task details window. Click the trash can icon to remove the relationship link, and then save.

Toggle to full screen for more workspace.

Use the drag and drop icon next to the task on the left hand column to move task location up or down to arrange in the desired order.

The zoom in and out icons change the scale from day, week, and month view.

Click the “Link In Sequence” to link all activities between the project start task and substantial completion task in a finish to start relationship and show activities in the critical path.

Click “Remove All Links” to unlink the sequence.

“Print” will create the PDF of the current view on-screen view. The schedule will automatically print for the full date range of the project. Update the date range to print look-ahead schedules.